The Rutgers Issues board was nuked and none of the posts were transferred here, so starting a new thread on the facilities construction projects.
Any updates on when Brower will be demoed and construction will start on the new CA quad? Demo started on records Hall in June 2022 and Brower in June 2023. Rumors back then were that Brower wouldn't be demoed for another 2+ years due to some utilities work, and a new dining hall wouldn't be ready until 2029 at the earliest. Will anything else be built with the new dining hall, like a new student center, dorm or academic building? Will Tate come out with 2040 master plans this year or in 2027? Thanks.I work for the department that is in charge of the master plan and it's definitely happening. The original plan was called Rutgers 2030 and with COVID that is probably more like 2040 at this point, but major aspects of the plan have already been built and will continue to be built. I can see the plan be revised so not everything in the original plan will be built, such as the boardwalk planned for the along the Raritan.